Project is nearing completion.
All civil works at the Lakes Entrance transfer station have been completed, including drainage works, asphalting, and line marking.
New signage is anticipated to be installed in the coming weeks.
Share Project Update 11/05/2023 on Facebook
Share Project Update 11/05/2023 on Linkedin
Email Project Update 11/05/2023 link
The three old bin bays were worked on during April to construct new edge beams and approach slabs. This work was completed.
The new gates and rails are currently being galvanised, and are expected to be installed during the week commencing 15 May 2023.
Next week (commencing 8 May), the drainage pit modifications in the bin forecourt area will be performed, allowing pavements to commence the following week (15 May).
Following finalisation of the crushed rock pavements, the sealing and asphalting can be performed.
Share Project Update 1/03/2022 on Facebook
Share Project Update 1/03/2022 on Linkedin
Email Project Update 1/03/2022 link
The Saw Tooth bays have been completed and works on the road sealing will commence in March
Share Project Update 9/02/2022 on Facebook
Share Project Update 9/02/2022 on Linkedin
Email Project Update 9/02/2022 link
Saw Tooth bay walls have been placed and back filling has begun.
Share Project Update 11/08/2021 on Facebook
Share Project Update 11/08/2021 on Linkedin
Email Project Update 11/08/2021 link
Work is also progressing, with the hardstand areas taking shape after the install of the drainage pipe work last week.
Share Project Update 28/07/2021 on Facebook
Share Project Update 28/07/2021 on Linkedin
Email Project Update 28/07/2021 link
Refurb works have continued this week, with the relocation of the green waste and metal pile to the new hardstand area.
Share Project Update 22/07/2021 on Facebook
Share Project Update 22/07/2021 on Linkedin
Email Project Update 22/07/2021 link
Refurbishment works have continued this week, with the Saw tooth bay location being readied for the instillation of the concrete retaining walls.