Project Update 11/05/2023
The three old bin bays were worked on during April to construct new edge beams and approach slabs. This work was completed.
The new gates and rails are currently being galvanised, and are expected to be installed during the week commencing 15 May 2023.
Next week (commencing 8 May), the drainage pit modifications in the bin forecourt area will be performed, allowing pavements to commence the following week (15 May).
Following finalisation of the crushed rock pavements, the sealing and asphalting can be performed.
Share Project Update 11/05/2023 on Facebook
Share Project Update 11/05/2023 on Twitter
Share Project Update 11/05/2023 on Linkedin
Email Project Update 11/05/2023 link
All civil works at the Lakes Entrance transfer station have been completed, including drainage works, asphalting, and line marking.