Lakes Entrance - Transfer Station refurbishment

Share Lakes Entrance - Transfer Station refurbishment on Facebook Share Lakes Entrance - Transfer Station refurbishment on Twitter Share Lakes Entrance - Transfer Station refurbishment on Linkedin Email Lakes Entrance - Transfer Station refurbishment link

Project Description
Upgrade of the existing Transfer Station to comply with industry best practice requirements.


Objectives and Scope
Install new saw tooth bays, hardstands and sealed roadways.


If you would like to search for other past, current or future projects in your town, simply type your town name in the search bar.

Project Description
Upgrade of the existing Transfer Station to comply with industry best practice requirements.


Objectives and Scope
Install new saw tooth bays, hardstands and sealed roadways.


If you would like to search for other past, current or future projects in your town, simply type your town name in the search bar.

  • Project Update - 17 January 2024

    Share Project Update - 17 January 2024 on Facebook Share Project Update - 17 January 2024 on Twitter Share Project Update - 17 January 2024 on Linkedin Email Project Update - 17 January 2024 link

    Project is nearing completion.

    All civil works at the Lakes Entrance transfer station have been completed, including drainage works, asphalting, and line marking.

    New signage is anticipated to be installed in the coming weeks.

  • Project Update 11/05/2023

    Share Project Update 11/05/2023 on Facebook Share Project Update 11/05/2023 on Twitter Share Project Update 11/05/2023 on Linkedin Email Project Update 11/05/2023 link

    The three old bin bays were worked on during April to construct new edge beams and approach slabs. This work was completed.

    The new gates and rails are currently being galvanised, and are expected to be installed during the week commencing 15 May 2023.

    Next week (commencing 8 May), the drainage pit modifications in the bin forecourt area will be performed, allowing pavements to commence the following week (15 May).

    Following finalisation of the crushed rock pavements, the sealing and asphalting can be performed.

  • Project Update 1/03/2022

    Share Project Update 1/03/2022 on Facebook Share Project Update 1/03/2022 on Twitter Share Project Update 1/03/2022 on Linkedin Email Project Update 1/03/2022 link

    The Saw Tooth bays have been completed and works on the road sealing will commence in March

  • Project Update 9/02/2022

    Share Project Update 9/02/2022 on Facebook Share Project Update 9/02/2022 on Twitter Share Project Update 9/02/2022 on Linkedin Email Project Update 9/02/2022 link

    Saw Tooth bay walls have been placed and back filling has begun.

  • Project Update 11/08/2021

    Share Project Update 11/08/2021 on Facebook Share Project Update 11/08/2021 on Twitter Share Project Update 11/08/2021 on Linkedin Email Project Update 11/08/2021 link

    Work is also progressing, with the hardstand areas taking shape after the install of the drainage pipe work last week.

  • Project Update 28/07/2021

    Share Project Update 28/07/2021 on Facebook Share Project Update 28/07/2021 on Twitter Share Project Update 28/07/2021 on Linkedin Email Project Update 28/07/2021 link

    Refurb works have continued this week, with the relocation of the green waste and metal pile to the new hardstand area.

  • Project Update 22/07/2021

    Share Project Update 22/07/2021 on Facebook Share Project Update 22/07/2021 on Twitter Share Project Update 22/07/2021 on Linkedin Email Project Update 22/07/2021 link

    Refurbishment works have continued this week, with the Saw tooth bay location being readied for the instillation of the concrete retaining walls.

Page last updated: 22 Feb 2024, 12:13 PM