An aerial view of the East Gippsland township of Bruthen, showing the Great Alpine Road intersection in the main street

About the Project

High priority on the community’s plan for their town, this project will support Bruthen’s transition from a timber-town to a tourism hub and important gateway to far East Gippsland and beyond. The works will facilitate new investment in the town, generate jobs and support the continued population growth in the areas immediately surrounding the town. The additional streetscape infrastructure will enhance the functionality of the main street and improve the towns amenity and public spaces to attract more people to local businesses, and encourage visitors and travellers to ‘stop, stay and spend’.

Three concept plans were initially developed and went out for community consultation in August 2021, please see attached. The concept plans look at removing unsafe intersections; widening carriageways to accommodate safe heavy vehicle movement and parking; improving parking to make it safer and meet current standards; and introducing pedestrian safety measures. Also included in the proposed upgrade is the enhancement of the main street garden areas with additional plantings; the refreshing of all street furniture; installation of new pedestrian paths to better connect destinations within the town centre; and an upgrade to one of Eastern Victoria’s most used public toilets. The feedback from the community consultation has guided the development of the final concept plan.

A business activation program will complement the physical works, to ensure that the works maximise economic growth. These works will include business workshops, events, advice on store layout and façade enhancement.

The development of the Bruthen Streetscape Project is to be the result of community collaboration and consultation along with key stakeholder input.

Community Consultation

The community consultation has now closed. Council representatives held three in person on-site community consultation sessions in August 2021, the representatives were able answer questions and to listen to your feedback during this process which was extremely valuable for the further development of the concept plan. The online survey has now closed, and all submissions have been reviewed. We thank everyone who took the time to attend the in-person sessions and take part in the online survey.

Budget

The budget for this project is provided through contributions from the Victorian Government and Council. Funding for this project is from the Victorian Government's Local Economic Recovery Program which is jointly funded by the Australian and Victorian Governments.



Should you wish to search for other projects in your town, simply type the name of your town in the search bar.

About the Project

High priority on the community’s plan for their town, this project will support Bruthen’s transition from a timber-town to a tourism hub and important gateway to far East Gippsland and beyond. The works will facilitate new investment in the town, generate jobs and support the continued population growth in the areas immediately surrounding the town. The additional streetscape infrastructure will enhance the functionality of the main street and improve the towns amenity and public spaces to attract more people to local businesses, and encourage visitors and travellers to ‘stop, stay and spend’.

Three concept plans were initially developed and went out for community consultation in August 2021, please see attached. The concept plans look at removing unsafe intersections; widening carriageways to accommodate safe heavy vehicle movement and parking; improving parking to make it safer and meet current standards; and introducing pedestrian safety measures. Also included in the proposed upgrade is the enhancement of the main street garden areas with additional plantings; the refreshing of all street furniture; installation of new pedestrian paths to better connect destinations within the town centre; and an upgrade to one of Eastern Victoria’s most used public toilets. The feedback from the community consultation has guided the development of the final concept plan.

A business activation program will complement the physical works, to ensure that the works maximise economic growth. These works will include business workshops, events, advice on store layout and façade enhancement.

The development of the Bruthen Streetscape Project is to be the result of community collaboration and consultation along with key stakeholder input.

Community Consultation

The community consultation has now closed. Council representatives held three in person on-site community consultation sessions in August 2021, the representatives were able answer questions and to listen to your feedback during this process which was extremely valuable for the further development of the concept plan. The online survey has now closed, and all submissions have been reviewed. We thank everyone who took the time to attend the in-person sessions and take part in the online survey.

Budget

The budget for this project is provided through contributions from the Victorian Government and Council. Funding for this project is from the Victorian Government's Local Economic Recovery Program which is jointly funded by the Australian and Victorian Governments.



Should you wish to search for other projects in your town, simply type the name of your town in the search bar.

  • 14 April 2025 - concrete poured!

    Share 14 April 2025 - concrete poured! on Facebook Share 14 April 2025 - concrete poured! on Twitter Share 14 April 2025 - concrete poured! on Linkedin Email 14 April 2025 - concrete poured! link

    Autumn sunshine meant perfect conditions for a concrete pour. The new pathways and picnic table area are complete, with a bench wall seat, featuring local stone, starting soon.

    Recently completed:

    • Concrete poured for the new pathways and picnic table area
    • The footings for the new stone seating have been completed


    Coming soon:

    • In the coming weeks, we will begin the stonework for the new seating areas, featuring locally sourced stone
    • We'll be working on the stand for the new bubbler tap soon
    • Additional roses and plants will embellish the rotunda when the weather suits planting
    • Turf aeration planned to improve growth and restore the lush green park
    • Maintenance schedule prepared to keep the gardens #pictureperfect


    Most of these works are happening near the existing toilet block. There may be some pedestrian impact within the park, however we expect minor disruptions during this time.

    We appreciate your patience and cooperation as we work to deliver these new additions. We look forward to completing this work soon. If you have any questions or concerns, we're here to help: 03 5153 9500 or feedback@egipps.vic.gov.au.

  • March 2025 - the final enhancements set to begin!

    Share March 2025 - the final enhancements set to begin! on Facebook Share March 2025 - the final enhancements set to begin! on Twitter Share March 2025 - the final enhancements set to begin! on Linkedin Email March 2025 - the final enhancements set to begin! link

    The final landscape enhancements are set to begin, with work scheduled to start in the third week of March 2025.

    The planned activities include:

    - Installing additional pathways and seating walls, featuring Bruthen stone

    - Positioning water bubblers

    - Turfing, mulching, and planting garden beds

    - Moving bins

    - Making minor tweaks to the irrigation system


    Most of these tasks will occur near the existing amenities, which may lead to some localised impacts within the park. We expect only minor disruptions during this time.

    This phase represents the last step of our efforts for this project, with input from the project reference group playing a crucial role in shaping the project’s scope and additional works.

    Thank you for your continued patience and support as we wrap up this upgrade.

  • 14 May 2024

    Share 14 May 2024 on Facebook Share 14 May 2024 on Twitter Share 14 May 2024 on Linkedin Email 14 May 2024 link

    Council's Works crew will be commencing construction of the footpaths at Bruthen toilet block on Wednesday 15 May 2024.The new footpaths around the toilet block will enhance accessibility and safety, making it easier for pedestrians to navigate the area.

    This work will be completed in stages to ensure access to the toilets will remain available throughout delivery of the project, which is anticipated to take just a few weeks.

    Upgrades to the existing toilet block will improve facilities for residents and visitors alike, ensuring better hygiene and convenience. Works will start as soon as we get an opportunity and will be completed by 30 June 2024. Plumbing supplies and internal partitions have already been ordered. We will start with the mens toilet, then progress with the other areas. We will ensure to keep disruptions to a minimum during this work.

    We will also be sprucing up the rotunda with new paint and cleaning the lichen off the roof.

    A new RV dump point has been ordered and will be installed in Lions Park to cater to the needs of travellers and tourists visiting Bruthen, enhancing the overall experience for RV users and encouraging more visitors to the area.

    These improvements will contribute to a more welcoming and functional community space in Bruthen. So much is happening, and we look forward to completion as soon as possible.




  • Project update - 2 August 2023

    Share Project update - 2 August 2023 on Facebook Share Project update - 2 August 2023 on Twitter Share Project update - 2 August 2023 on Linkedin Email Project update - 2 August 2023 link

    The stone wall seating is finished. The stone is locally sourced Bruthen Blue Sandstone. Native vegetation and well-designed landscaping will soften the rock and create an enjoyable space for all generations to enjoy.


  • Project Update - 22 May 2023

    Share Project Update - 22 May 2023 on Facebook Share Project Update - 22 May 2023 on Twitter Share Project Update - 22 May 2023 on Linkedin Email Project Update - 22 May 2023 link
    supporting image

    Progress - a new bus shelter and new picnic table settings and bike racks have been installed.

    The service road has been completed.

    Minor landscaping will be finalised in the coming weeks.

  • Project Update 27/04/2023

    Share Project Update 27/04/2023 on Facebook Share Project Update 27/04/2023 on Twitter Share Project Update 27/04/2023 on Linkedin Email Project Update 27/04/2023 link
    supporting image

    Works on the new Bruthen Streetscape are progressing well and are on schedule to be completed by mid-2023.

    Civil works completed to date:

    • Construction of kerb and channel, together with the associated drainage works such as pits and pipes.
    • Driveway construction.
    • Bitumen asphalt work, with line marking to follow shortly.
    • Bus shelter to be erected soon.

    Council crews will soon commence construction on landscaping and toilet facilities.

  • Project Update 23/03/2023

    Share Project Update 23/03/2023 on Facebook Share Project Update 23/03/2023 on Twitter Share Project Update 23/03/2023 on Linkedin Email Project Update 23/03/2023 link
    supporting image

    Bruthen Streetscape construction is continuing to take shape, with kerb, channel, and roadway being completed prior to Easter (weather dependant).

    Construction of kerbing on the southern side of Main Street, and the outstand (for pedestrian crossing) on the Great Alpine Road northern side is continuing.

    There are many photos showing the progression of construction works in the photos section of YourSay.

  • Project Update 31/01/2023

    Share Project Update 31/01/2023 on Facebook Share Project Update 31/01/2023 on Twitter Share Project Update 31/01/2023 on Linkedin Email Project Update 31/01/2023 link
    supporting image

    Construction on the new Bruthen Streetscape project commenced on Monday 30 January 2023.

    Council workers will be undertaking some of the works, for example, new gardens, and the replacement and installation of picnic benches. The works are limited to the west side of the Main Street for the moment. GLaWAC are working on a yarning circle design and will provide a design when completed.

  • Project update 17/01/2023

    Share Project update 17/01/2023 on Facebook Share Project update 17/01/2023 on Twitter Share Project update 17/01/2023 on Linkedin Email Project update 17/01/2023 link
    supporting image

    Council's Works Unit is currently working at replacing the existing picnic tables with new ones and installing additional DDA compliant tables within the western median area.

    Council's Parks and Gardens Unit will commence construction on the new garden bed locations in the coming weeks. All works will be carried out in accordance with the landscaping plans which are provided in the documents section.

  • Project Update 23/11/2022

    Share Project Update 23/11/2022 on Facebook Share Project Update 23/11/2022 on Twitter Share Project Update 23/11/2022 on Linkedin Email Project Update 23/11/2022 link

    The MOU with the Department of Transport is still to be finalised for this project. Road pavement works will now commence early 2023.

    Council’s Parks and Garden Unit have removed the roses from the gardens beds and will remove the brick edging and the excess topsoil/mulch to make way for the rotunda relocation and civil works to begin.

    Council’s maintenance crew will install the picnic table sets and construct the footpaths.

    Street furniture has been ordered and will be transported to the Bruce Road depot in January 2023.