05 August 2021
Survey opens
12 August 2021
Face to face community consultation 1 pm - 2 pm
19 August 2021
Face to face community consultation 4 pm - 5 pm
21 August 2021
Face to face community consultation 9.30 am - 10.30 am
31 August 2021
Survey closes
01 May 2022
Community Consultation for landscape works commences
21 May 2022
Community Consultation Complete
January 2023
Construction to begin
April 2023
Construction of the road & drainage modifications to be completed
November 2022
Landscape detail drawings have been completed
June 2023
Toilet and landscape construction to be finalised