Share Project Update 1/03/2023 on Facebook
Share Project Update 1/03/2023 on Linkedin
Email Project Update 1/03/2023 link
Share Project Update 23/02/2023 on Facebook
Share Project Update 23/02/2023 on Linkedin
Email Project Update 23/02/2023 link
Due to regular flooding occurring south of the Bill Creek Bridge on Wairewa Road works were programmed to mitigate further flooding and to improve access for all road users.
The works began on Sunday 19 February and continued night and day to ensure the road closure had minimal effect on the community.
Works are nearing completion and the road is expected to be re-opened on Friday 24 February.
Share Project Update 19/01/2023 on Facebook
Share Project Update 19/01/2023 on Linkedin
Email Project Update 19/01/2023 link
ROAD CLOSURE NOTIFICATION – AMENDED DATES
WAIREWA ROAD, BILLS CREEK
Wairewa Road, Bills Creek will be closed from 19th to 22nd February 2023 inclusive in order to undertake urgent maintenance works.
Council have awarded the flood mitigation project at Bills Creek to Whelans Group Investments Pty Ltd. The project sees the installation of two large box culverts and raising the level of the road. The plan is to close Wairewa Road at Bills Creek for five days to enable Whelans to work day and night and complete the works and reopen the road to traffic.
The previous option of staging the works and keeping one lane open to traffic proved to be extremely difficult, due to limitations in work space, saturated ground conditions and utility service locations. This option would have seen the road reduced to one lane for ten days and have caused long delays for road users.
Signage will be installed on Wairewa Road, 14 days prior to the road closure.
East Gippsland Shire Council apologises for any inconvenience that may be caused.
Should you have any queries, please do not hesitate to contact Sean Heinemann, Project Supervisor on 03 5153 9500.
Share Project Update 10/01/2023 - Road Closure Notification on Facebook
Share Project Update 10/01/2023 - Road Closure Notification on Linkedin
Email Project Update 10/01/2023 - Road Closure Notification link
Wairewa Road, Bills Creek will be closed from 13th to 17th February 2023 inclusive in order to undertake urgent maintenance works.
Council have awarded the flood mitigation project at Bills Creek to Whelans Group Investments Pty Ltd. The project sees the installation of two large box culverts and raising the level of the road. The plan is to close Wairewa Road at Bills Creek for five days to enable Whelans to work day and night and complete the works and reopen the road to traffic.
The previous option of staging the works and keeping one lane open to traffic proved to be extremely difficult, due to limitations in work space, saturated ground conditions and utility service locations. This option would have seen the road reduced to one lane for ten days and have caused long delays for road users.
Signage will be installed on Wairewa Road, 14 days prior to the road closure.
East Gippsland Shire Council apologises for any inconvenience that may be caused.
Should you have any queries, please do not hesitate to contact Sean Heinemann, Project Supervisor on 03 5153 9500.
Share Project Update 24/11/2022 - Flood Mitigation Works - Temporary Road Closure on Facebook
Share Project Update 24/11/2022 - Flood Mitigation Works - Temporary Road Closure on Linkedin
Email Project Update 24/11/2022 - Flood Mitigation Works - Temporary Road Closure link
ROAD CLOSURE NOTIFICATION
WAIREWA ROAD, BILLS CREEK
Wairewa Road, Bills Creek will be closed for approximately three days in early February 2023 in order to undertake urgent maintenance works. A second notification will follow as soon as exact dates are known.
Council have awarded the flood mitigation project at Bills Creek to Whelans Group Investments Pty Ltd. The project sees the installation of two large box culverts and raising the level of the road. The plan is to close Wairewa Road at Bills Creek for three days to enable Whelans to work day and night and complete the works and reopen the road to traffic.
The previous option of staging the works and keeping one lane open to traffic proved to be extremely difficult, due to limitations in work space, saturated ground conditions and utility service locations. This option would have seen the road reduced to one lane for ten days and have caused long delays for road users.
Signage will be installed on Wairewa Road, 14 days prior to the road closure.
East Gippsland Shire Council apologises for any inconvenience that maybe caused.
Should you have any queries, please do not hesitate to contact Sean Heinemann, Project Supervisor on 03 5153 9500.
SAIRAM JEGATHEESWARAN
Manager Capital Projects and Plant