Construction Packages 1 & 2 (Cranes) are progressing toward a February 2023 completion. It is anticipated that the grass hockey pitch will be open during summer holidays.

The synthetic hockey pitch and netball courts surfacing will be completed by February 2023. The project supervisor is awaiting permanent power energisation advice from AusNet (forecast by the end of the year).