Project Update - 14 September 2023
All works on the netball courts and carpark are now complete, including the balustrade and placement of the netball post padding.
The Netball Association are now able to use the courts during daylight hours.
The power connection to the precinct is progressing and is scheduled for energization early October. The lighting systems will then require adjusting and certification to the required lux levels as per the current sporting standards.
- Hockey complex – synthetic pitch complete, grass pitch almost complete (further irrigation works will be undertaken once the power connection is complete)
- Access roads, paths, car parking and landscaping are all complete
- Pavilion 1 - Netball Marshall building is complete
- Pavilion 2 - WORLD pavilion is currently under construction (see photos)
Share Project Update - 14 September 2023 on Facebook
Share Project Update - 14 September 2023 on Twitter
Share Project Update - 14 September 2023 on Linkedin
Email Project Update - 14 September 2023 link