Paynesville - Dinni Birraark Walk
The improvement of the current condition of the Dinni Birraark Walk in Paynesville was identified by the Paynesville Landcare Coastcare group and adopted in the Paynesville Foreshore Management Plan.
Project Update 8 June 2023
The rock beaching works are 100 % complete and construction of the walking trail (pavement work) was started on 24 May 2023.This project aims to repair and reinstate the rock wall adjoining the Kalimna foreshore and walking trail.
Mallacoota - Bastion Point groyne wall
project updates provided in the tab belowRemediation works for the short-term improvement of the Bastion Point rock wall commenced in 2023.
Project Update - 13 December 2023
Jemmys Point webcam - click to view
Walking trail closed 11 September to 30 November 2023
Loop Trail is a component of Council's Jemmy's Point Stage 2 project.
Project Update - 9 November 2023
Cranes Civil and Surfacing have progressed construction works on three of the new crushed rock walking trails; the Jetty access trail in Kalimna, the Jemmys Point Reserve to Point Road trail, and the Jetty walk link trail.
17 December 2024
The foreshore boardwalk is visited by many residents and tourists, and is a major attraction for those visiting East Gippsland.
Lakes Entrance - Krauatungalung Walk
The circuit aims to complement and link the existing uses and facilities of the Lakes Entrance foreshore.
Metung - Shaving Point Boat Ramp
The upgrade of the Shaving Point boat ramp is now complete - Media ReleaseCouncil is pleased to have received funding from Better Boating Victoria to assist with an upgrade of this well used boat ramp in Metung.The works to be undertaken include the demolition
Project Update 13/04/2023
Site design investigations will be carried out on Tuesday 18/04/23 and Wednesday 19/04/23 to assess Shaving Point for a proposed future upgrade.