Bairnsdale - Day Street

Day Street will be resurfaced on Saturday 28 October 2023 and Sunday 29 October 2023.

Traffic management will be in place to ensure access to the Emergency Department.

Reduced access Limited parking

The Bairnsdale Hospital carpark in Day Street is scheduled for resurfacing and renewal of all line marking on the weekend of 28 – 29 October 2023, weather permitting. Fowlers Asphalting will be undertaking the works and will only close half of the car park each day to minimise the impact on hospital parking.

Visitors to the area are asked to observe construction signage and any directions from the contractor, including following traffic management direction in the precinct during the works.

To read more, visit - Bairnsdale - Day Street

Share Bairnsdale - Day Street on Facebook Share Bairnsdale - Day Street on Twitter Share Bairnsdale - Day Street on Linkedin Email Bairnsdale - Day Street link

The Road Reseal Program 2023-2024 has been completed.

Sixty-six (66) roads across East Gippsland were resealed, amounting to approximately thirty-eight (38) kilometres of reseal works delivered.

Delivery of this annual program is informed by Council's Asset Management Plan, with roads selected based on their condition and level, with priority given toward adjacent roads to reduce mobilisation expenses.

The 2023-2024 Road Reseal Program was predominately funded by Council cash, with some roads included in the Australian Government Roads to Recovery Program.