Gilsenan Reserve Upgrade – Works Update April

Good progress is being made at Gilsenan Reserve, with key early works now complete and construction about to begin on the new toilet block.

Project update:

  • Sewer connection works have been completed by Cal Civil
  • All affected areas have been reinstated and are ready for the next stage
  • Design Co Builders are scheduled to start on site from 27 April to begin construction of the new toilet block
  • Minor works may occur outside the main site area to connect water and power services during construction
  • A new crossover has been installed by Krammes Mini Earthmoving to improve access to the reserve. The crossover location was chosen in partnership with the Paynesville Lions Club to maintain safe access for community and reserve events

Thank you to the community for your patience and support as this important upgrade continues. Further updates will be shared as works progress.