Omeo - Revitalising Livingstone Park Upgrade

Share Omeo - Revitalising Livingstone Park Upgrade on Facebook Share Omeo - Revitalising Livingstone Park Upgrade on Twitter Share Omeo - Revitalising Livingstone Park Upgrade on Linkedin Email Omeo - Revitalising Livingstone Park Upgrade link

Project updates are provided in the tab below.


Project Background

Council secured funding from Emergency Recovery Victoria in 2021 through the Local Economic Recovery Program to revitalise Livingstone Park in Omeo.

The following year, multiple flood events caused significant damage to the banks of Livingstone Creek and park infrastructure.

Emergency remedial protection works were carried out by our maintenance contractors to reinstate carparking and pedestrian access and to stabilise the banks of the creek and protection of the pump track. Hydrology investigations and engineering advice were completed to ensure safe public use and the park's long-term future. 

Flood mitigation works will now take priority to protect existing public assets from flood impact and provide opportunity for this central public space to be revitalised in the future.

Objective and scope

The project will include flood-disaster risk-mitigation actions, along with ongoing protection and management of both cultural and environmental assets such as Livingstone Creek, which is the major focal point of the park.

Works within this project include:

  • Earthworks and bank stabilisation works
  • Vegetation, topsoil, and seed placement
  • Rock chute
  • Reconstruction of the damaged spillway and pedestrian bridge

The mitigation works will ensure the 24-hectare centrepiece of Omeo will continue to provide a public space where the community can come together, recreate and improve community well-being and resilience.

Funding

Funding is provided by Emergency Recovery Victoria and East Gippsland Shire Council

Project updates are provided in the tab below.


Project Background

Council secured funding from Emergency Recovery Victoria in 2021 through the Local Economic Recovery Program to revitalise Livingstone Park in Omeo.

The following year, multiple flood events caused significant damage to the banks of Livingstone Creek and park infrastructure.

Emergency remedial protection works were carried out by our maintenance contractors to reinstate carparking and pedestrian access and to stabilise the banks of the creek and protection of the pump track. Hydrology investigations and engineering advice were completed to ensure safe public use and the park's long-term future. 

Flood mitigation works will now take priority to protect existing public assets from flood impact and provide opportunity for this central public space to be revitalised in the future.

Objective and scope

The project will include flood-disaster risk-mitigation actions, along with ongoing protection and management of both cultural and environmental assets such as Livingstone Creek, which is the major focal point of the park.

Works within this project include:

  • Earthworks and bank stabilisation works
  • Vegetation, topsoil, and seed placement
  • Rock chute
  • Reconstruction of the damaged spillway and pedestrian bridge

The mitigation works will ensure the 24-hectare centrepiece of Omeo will continue to provide a public space where the community can come together, recreate and improve community well-being and resilience.

Funding

Funding is provided by Emergency Recovery Victoria and East Gippsland Shire Council

  • Project Update - 21 February 2024

    Share Project Update - 21 February 2024 on Facebook Share Project Update - 21 February 2024 on Twitter Share Project Update - 21 February 2024 on Linkedin Email Project Update - 21 February 2024 link

    Council is currently reviewing the concept plans to ensure they remain accurate following the flooding events last year. Further updates will be provided once the review process has been completed.

    We welcome your continued interest in this project; project updates will be provided on YourSay, when available. Please click on 'Subscribe' at the top of the page to follow this project and to receive important information directly to your inbox.