    Streamology have been engaged for the design of flood remediation works.

    Streamology have already completed hydrology and hydraulic modelling to inform the design and achieve a long-term stabilisation of the creek. Although the concept of a rock chute is simple, proper hydraulic design is critical to ensure that the chute geometry and rock size are matched with the expected flow conditions such that the rock remains stable under all expected flow conditions. The detailed design has now been finalised and includes elements such as rock chutes and a rock crossing.

    Officers of the North-East Catchment Management Authority (NECMA) also provided valuable input to the design process.

    Council has commenced the process of seeking permits and approvals for the construction works. Whilst we finalise this process, the construction works will be advertised for tendering.

    The construction works are expected to commence in February and be completed by June 2025 to meet our grant deadline.

    Streamology have been engaged for the design of flood remediation works.

    Streamology have already completed hydrology and hydraulic modelling to inform the design and achieve a long-term stabilisation of the creek. Although the concept of a rock chute is simple, proper hydraulic design is critical to ensure that the chute geometry and rock size are matched with the expected flow conditions such that the rock remains stable under all expected flow conditions. The detailed design has now been finalised and includes elements such as rock chutes and a rock crossing.

    Officers of the North-East Catchment Management Authority (NECMA) also provided valuable input to the design process.

    Council has commenced the process of seeking permits and approvals for the construction works. Whilst we finalise this process, the construction works will be advertised for tendering.

    The construction works are expected to commence in February and be completed by June 2025 to meet our grant deadline.

  • 21 March 2024

    Share 21 March 2024 on Facebook Share 21 March 2024 on Twitter Share 21 March 2024 on Linkedin Email 21 March 2024 link

    A request for quote is currently advertised for the completion of detailed design for the flood remediation works.

    To be a part of this exciting project, submit your application at - Tenders (eastgippsland.vic.gov.au)

    Open until 17 April 2024.

    A request for quote is currently advertised for the completion of detailed design for the flood remediation works.

    To be a part of this exciting project, submit your application at - Tenders (eastgippsland.vic.gov.au)

    Open until 17 April 2024.

  • Project Update - 21 February 2024

    Share Project Update - 21 February 2024 on Facebook Share Project Update - 21 February 2024 on Twitter Share Project Update - 21 February 2024 on Linkedin Email Project Update - 21 February 2024 link

    Council is currently reviewing the concept plans to ensure they remain accurate following the flooding events last year. Further updates will be provided once the review process has been completed.

    We welcome your continued interest in this project; project updates will be provided on YourSay, when available. Please click on 'Subscribe' at the top of the page to follow this project and to receive important information directly to your inbox.

    Council is currently reviewing the concept plans to ensure they remain accurate following the flooding events last year. Further updates will be provided once the review process has been completed.

    We welcome your continued interest in this project; project updates will be provided on YourSay, when available. Please click on 'Subscribe' at the top of the page to follow this project and to receive important information directly to your inbox.