Project Update - 19 September 2023
We have experienced a small delay, with the extra piling taking additional time to complete.
Completion of this project has been revised to the second week of October 2023.
The floating jetty abutment is underway, with concrete to be poured on Wednesday 20 September 2023. | The asphalt has been cut back ready for the new asphalt, then the new apron is complete. |
The fixed jetty only needs the top deck installed - this is scheduled to arrive this week. |