Project Update - 21 August 2023
Community feedback on the draft car parking design is being used to inform further development of the design plans to provide more parking.
Streeter Civil Engineering Services Pty. Ltd. has been engaged to undertake detailed design. The initial design included five new carparks; however, the new design will provide more than double the original amount. A disabled carpark, new kerb and channel, and associated drainage works will also be included.
Once the detail design is complete, tender for construction will be released.
Due the increased project scope and subsequent price increase, commencement of construction is subject to future funding availability.
The upgrade to the Greer Street Sports Pavilion Carpark in Mallacoota was completed in May 2024.