Project Update - 23 October 2023
The playground is really taking shape, with our in-house crew preparing the concrete around the play equipment ready for the rubber soft fall to be installed.
Stepping logs and balance logs are scheduled to be delivered later this week. Once the logs are installed, the soft fall materials will be laid, and garden areas completed. The basket swing and child swing seats will be installed following the placement of the soft fall materials.