Project Update - 17 August 2023

Have you seen us on site at the new Eastwood Play Space this week?

The concrete footpath has been poured around the area marked out for the play equipment and the project is progressing well. The concreting was done by Fox Martin Concrete and Construction on behalf of Friths Plumbing and Civil Construction, who were awarded the contract for the civil works and concrete package.

The connection to the carpark will be completed the first week of the September school holidays.

Our Council crew will work together with Adventure+ to install the play equipment in mid-late September. Landscaping will commence once the play equipment is in.