East Gippsland - Timber Bridge Replacement Program

Share East Gippsland - Timber Bridge Replacement Program on Facebook Share East Gippsland - Timber Bridge Replacement Program on Twitter Share East Gippsland - Timber Bridge Replacement Program on Linkedin Email East Gippsland - Timber Bridge Replacement Program link

East Gippsland Shire Council's timber bridge replacement program is nearing completion. In the past 9 years over 153 timber bridges have been replaced with steel and concrete bridges, or where possible, major culverts. The new bridges have a 100 year design life and a load capacity of up to 68 tonne, and are less prone to impacts by fires or floods.

Council's timber bridge replacement prioritisation model is determined by the following factors:

  • Load limitations
  • Usage
  • Place
  • Possibility of impact from natural disaster
  • Singular access/Alternate route available
  • Access / egress
  • Maintenance costs
ROAD NAME LOCATIONSCHEDULED FOR REPLACEMENTSTATUS
Bouchers Lane

Jarrahmond

2023/24

completed
August 2023
Glen Arte Road

Arte River, Cabbage Tree Creek

2023/24

completed
October 2023
Little River Road

Morass Creek, Ensay North

2023/24

completed
March 2024
Suttons Access Road

Combienbar River access bridge

2023/24

completed
November 2023
Upper Wingan Road

Scrubby Creek, Genoa

2023/24

completed
December 2023
WB Line Track

Chandlers Creek, Cann River

2023/24

completed
October 2023
West Bridge Road

Rocky River, Cabbage Tree Creek

2023/24

completed
November 2023
James Road

Orbost

2023/24

Completed
March 2024
Reedy Creek Road

Reedy Creek, Ensay

2023/24 Completed
May 2024


Bridges to be completed in FY 2024/25:

Gulf RoadBendoc River, Bendoc
Nodens Access TrackDouble Creek, Genoa


Bridges to be completed in future years:

Healeys RoadCabbage Tree
Hollonds O'Briens RoadTambo River, Swifts Creek
Lees RoadRailway Line, Mossiface


East Gippsland Shire Council's timber bridge replacement program is nearing completion. In the past 9 years over 153 timber bridges have been replaced with steel and concrete bridges, or where possible, major culverts. The new bridges have a 100 year design life and a load capacity of up to 68 tonne, and are less prone to impacts by fires or floods.

Council's timber bridge replacement prioritisation model is determined by the following factors:

  • Load limitations
  • Usage
  • Place
  • Possibility of impact from natural disaster
  • Singular access/Alternate route available
  • Access / egress
  • Maintenance costs
ROAD NAME LOCATIONSCHEDULED FOR REPLACEMENTSTATUS
Bouchers Lane

Jarrahmond

2023/24

completed
August 2023
Glen Arte Road

Arte River, Cabbage Tree Creek

2023/24

completed
October 2023
Little River Road

Morass Creek, Ensay North

2023/24

completed
March 2024
Suttons Access Road

Combienbar River access bridge

2023/24

completed
November 2023
Upper Wingan Road

Scrubby Creek, Genoa

2023/24

completed
December 2023
WB Line Track

Chandlers Creek, Cann River

2023/24

completed
October 2023
West Bridge Road

Rocky River, Cabbage Tree Creek

2023/24

completed
November 2023
James Road

Orbost

2023/24

Completed
March 2024
Reedy Creek Road

Reedy Creek, Ensay

2023/24 Completed
May 2024


Bridges to be completed in FY 2024/25:

Gulf RoadBendoc River, Bendoc
Nodens Access TrackDouble Creek, Genoa


Bridges to be completed in future years:

Healeys RoadCabbage Tree
Hollonds O'Briens RoadTambo River, Swifts Creek
Lees RoadRailway Line, Mossiface


East Gippsland Shire Council is limited in the community engagement it can undertake during the Council Election Period, 17 September 2024 to 26 October 2024. Further updates will be provided following the Council Election on 26 October 2024 and the questions/feedback tab will be reinstated.

Your questions will be sent to the Project Supervisor.  The Project Supervisor's response can be posted publicly or privately - please let us know if you would prefer to be answered privately.

Page last updated: 17 Sep 2024, 10:19 AM