February - March 2025 progress update
Netball and Tennis Court
Everyone's buzzing with excitement as significant progress is made on the netball and tennis courts.
The new light poles and lights have been installed and tested, ensuring bright and safe play areas. The new asphalt will soon be ready for the contractor to begin preparations for coating and line marking. Weather permitting, the coating is expected to be completed by the end of March 2025.
The court fencing is nearly finished, with gates soon to be installed. Following the coating, netball rings and tennis posts will be set up, complementing the already installed basketball ring.
A power upgrade is scheduled, with SP Ausnet installing a new pole and transformer in the first week of April 2025. We are eagerly awaiting the power connection date to light up the new courts.
Pavilion Project
The pavilion project is also on track. All concrete footings are complete, along with some stormwater drainage and pits.
The pavilion will feature a robust steel frame with a timber substructure, promising a sturdy and welcoming facility for all. With 80% of the steel subfloor delivered, contractors have begun erecting it.
The builder remains on schedule, aiming for completion in 2026.
Stay tuned for more updates as these exciting projects continue to unfold!
![]() |
![]() |
![]() |