1 May 2025
🏐 Netball courts
- Court surface & markings - the court coating and line marking have been successfully completed.
- Fixtures & handover - All court fixtures have been installed. The courts have now been officially handed over and are available for netball training and games.
- Electrical infrastructure - SP AusNet has completed the installation of the new power pole and transformer on the street, along with the underground cabling.
- Lighting status - The netball court lights remain non-operational until SP AusNet completes the final power connection.
-
Power connection follow-up - we have been actively engaging with SP AusNet to secure a connection date. However, a confirmed timeline for the power connection has not yet been provided.
Pavilion construction
-
Steelwork Installation:
- 100% of the pavilion steelwork has been delivered to site.
- Approximately 95% of the subfloor steel and 80% of the roof structure have been installed.
- Steel erection will continue over the coming weeks.
Carpentry works - carpenters are currently installing floor joists onto the steel bearers as part of the next construction phase.
Project timeline - the builder remains on schedule with the current works program, targeting project completion in 2026.
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |