1 May 2025

🏐 Netball courts

  • Court surface & markings - the court coating and line marking have been successfully completed.
  • Fixtures & handover - All court fixtures have been installed. The courts have now been officially handed over and are available for netball training and games.
  • Electrical infrastructure - SP AusNet has completed the installation of the new power pole and transformer on the street, along with the underground cabling.
  • Lighting status - The netball court lights remain non-operational until SP AusNet completes the final power connection.
  • Power connection follow-up - we have been actively engaging with SP AusNet to secure a connection date. However, a confirmed timeline for the power connection has not yet been provided.

Pavilion construction

  • Steelwork Installation:

    • 100% of the pavilion steelwork has been delivered to site.
    • Approximately 95% of the subfloor steel and 80% of the roof structure have been installed.
    • Steel erection will continue over the coming weeks.
  • Carpentry works - carpenters are currently installing floor joists onto the steel bearers as part of the next construction phase.

  • Project timeline - the builder remains on schedule with the current works program, targeting project completion in 2026.