Netball /Tennis courts

  • The proof roll and compaction test for the 1st layer of the court base has been ticked off.
  • The court contractor will bring in stabilising material and compact it over the next few weeks.
  • The steel reinforcement cages for the light poles have been delivered; the light pole footings to be excavated soon.
  • Our fencing contractor is scheduled to start works shortly as many of these components need to be in before the concrete works can occur.
  • Structural plans for the rebound wall have been approved and the contractor has placed the order for production.

Pavilion

  • A building permit for the new pavilion has been issued.
  • The builders now have possession of the site.
  • Set out of the new pavilion works to take place this week.