9 September 2024

Our contractor for the netball/tennis court construction is bringing in additional fill from the local quarry to reach the subbase level. Compaction of this material is scheduled to occur in the next few days.

The demolition of the existing toilet block was completed on Tuesday, and site cleanup will continue throughout this week. A request for quote will be released in the coming weeks for the mobile tennis net.

A contract has been signed and a site meeting held with Cadbuild Construction Pty Ltd, contractor for the changeroom pavilion. The construction schedule is being prepared with a tentative start date of early November 2024, pending building approvals.

Demolished changerooms and toilet block area.

Existing court Asphalt stripped, and fill being placed up to the subbase.

Local quarry material being placed.



We welcome your continued interest in this project. Please choose to follow this project on YourSay to receive important information directly to your inbox.