18 December 2024

Sports courts

  • The proof roll and compaction test for the 2nd layer of court base has been approved.
  • Most of the perimeter fence posts have been installed so our concreter can start the formwork for the spoon drain and concrete pathways beside the netball court.
  • The steel reinforcement cages for the light poles have been delivered and pole footings will be dug in the new year.
  • The rebound hit-up wall concrete panel has been made off site and ready for delivery and installation in the new year.
  • We are hoping that asphalt will be installed late January [weather permitting].


Pavilion

Set out of the new pavilion works has taken place with the builder excavating and pouring more than 50% of the building's footings.