Project Update 23/11/2022
The new Lucknow Gymnastics Pavilion is progressing well. The roof is now fully covered with purlin rubber and riveting will soon be completed.
- The sunken pit for the trampolines is well underway.
- Concrete was poured for the floor to the east 1/3 of the building.
- Timber framing and flooring has been delivered for the toilet, office, and mezzanine areas. Framing will begin on the office and toilet areas on Monday.
- Windows and front entry slider are installed.
- Concrete to the front path and services area will be set up Thursday 24 November, with a pour early next week.