Project Updates 2021
11/08/2021 - Bairnsdale Cell 4 excavation work is progressing well and it is expected that if the good weather continues, we will near the design floor of the pit within the next few weeks.
5/08/2021 - Bairnsdale Cell 4 excavation work continues, with some decent weather allowing the subcontractor to realise that they are gradually getting towards the bottom of the dig.
28/07/2021 - Bairnsdale Cell 4 excavation work continues, with some of the soil stockpile already being removed and repurposed on other council projects
22/07/2021 - Bairnsdale Cell 4 excavation works continue, with a steady flow of earth continuing to being excavated on site.
14/07/2021 - Excavation works continue, with a steady flow of earth continuing to being excavated on site.
30/06/2021 - Excavation works continue, with the dryer weather ensuring a steady flow of earth being shifted on site.
23/06/2021 - Excavation works continue, with the merging of the existing Cell 3B and new Cell 4 starting.
16/06/2021 - Bairnsdale Cell 4 slowly continued this week after a heavy rain delay, with excavation works of the new cell progressing well. Soil testing continues with all test coming back with no issues to this point.
2/06/2021 - Bairnsdale Cell 4 continued this week, with excavation and Stockpiling of clay for reuse in the new cell. More material testing along with confirmation of Liner materials have being ordered, but again overall works are progressing well.
26/05/2021 - Bairnsdale Cell 4 continued this week after a short rain delay, with excavation works of the new cell well under way. Liner materials are being ordered along with soil materials being readied for testing, but overall works are progressing well.
This project is now complete