Bairnsdale - Cell 4 - Bairnsdale Landfill
Updates
Unfortunately there is no further progress with Bairnsdale Landfill Cell 4 still on hold. Council are expecting the contractors who are installing the liners to arrive on site this week (weather permitting). Further updates will be provided once this occurs.
For further updates on the progress of the project please see the News Feed tab below
Past Updates
9/02/2022 - Cell 4 is on hold for the next couple of weeks as we await the arrival of the lining crews who are behind schedule due to inclement weather on their current projects.
11/08/2021 - Bairnsdale Cell 4 excavation work is progressing well and it is expected that if the good weather continues, we will near the design floor of the pit within the next few weeks.
5/08/2021 - Bairnsdale Cell 4 excavation work continues, with some decent weather allowing the subcontractor to realise that they are gradually getting towards the bottom of the dig.
28/07/2021 - Bairnsdale Cell 4 excavation work continues, with some of the soil stockpile already being removed and repurposed on other council projects
22/07/2021 - Bairnsdale Cell 4 excavation works continue, with a steady flow of earth continuing to being excavated on site.
14/07/2021 - Excavation works continue, with a steady flow of earth continuing to being excavated on site.
30/06/2021 - Excavation works continue, with the dryer weather ensuring a steady flow of earth being shifted on site.
23/06/2021 - Excavation works continue, with the merging of the existing Cell 3B and new Cell 4 starting.
16/06/2021 - Bairnsdale Cell 4 slowly continued this week after a heavy rain delay, with excavation works of the new cell progressing well. Soil testing continues with all test coming back with no issues to this point.
2/06/2021 - Bairnsdale Cell 4 continued this week, with excavation and Stockpiling of clay for reuse in the new cell. More material testing along with confirmation of Liner materials have being ordered, but again overall works are progressing well.
26/05/2021 - Bairnsdale Cell 4 continued this week after a short rain delay, with excavation works of the new cell well under way. Liner materials are being ordered along with soil materials being readied for testing, but overall works are progressing well.
Information last updated by Project Supervisor on 9/02/2022
If you would like to search for other past, current or future projects in your town, simply type your town name in the search bar.