Project Updates

Courts

The netball and tennis courts were recently tendered for construction and we are excited to announce that a contract has been awarded with works to commence in November. Works will be undertaken by local contractors – J W Volk Pty Ltd and will be completed prior to the 2023 netball season.

Pavilion/change rooms

Due to a granted budget that is fixed and continuing challenges with cost escalations (far wider than East Gippsland), in partnership with the Project Control Group, the pavilion and change rooms have undergone a redesign. The redesign work is close to completion and construction tender documentation due for release prior to Christmas.