Whatβs been achieved so far
- Site preparation & demolition
In June 2025, site fencing was installed and the old Sarsfield Hall was demolished to make way for the new facility. -
Foundations & structure
- Site set-out completed
- Board piers poured with hold-down bolts for a strong foundation
- Structural steel erected
- Concrete poured for both north and south ends of the building
-
Building progress
- Roof trusses installed and roof completed
- Windows installed
- Brickwork completed
- Electrical, plumbing, and mechanical rough-in finished
- Plastering completed and painting underway
- Joinery delivered and installation commenced
- Building fully locked up and site cleaned for the Christmas break
Current status
- External drainage works are underway
- Eave and soffit lining continuing
- Wet areas prepared for vinyl flooring
Whatβs next
The team is currently on a short Christmas break, with works set to resume shortly. Upcoming activities include:
- Final painting and joinery installation
- Flooring in wet areas
- External finishes and landscaping
Looking ahead
Despite a few minor weather delays earlier in the project, the timeline remains on track. The new Sarsfield Community Centre is shaping up to be a fantastic space for the community, and weβre excited to see it nearing completion.