Nicholson Street Progress update April 2026

Works are continuing on the Nicholson Street footpath renewal, with good progress being made.

Project progress:

  • New concrete footpath construction is underway from Clarke Street toward McLeod Street
  • Works have reached approximately the halfway point between Clarke Street and McLeod Street
  • Exposed aggregate edging is being installed to match the existing streetscape
  • The renewed footpath will improve safety and accessibility for pedestrians

Works will continue toward McLeod Street end of Nicholson Street, and Council thanks the community for their patience during construction.