Project Update 21/03/2023

Taking shape

Trail building is pushing towards the completion of about 10km of trails to be ride ready by Easter. The construction of trails continues concurrently on other Stage 1 and 2 sections.

Fabrication of a significant piece of trail crossover structure, which will allow riders to pass under and over one another on different trails near the swimming pool at the Livingstone Park trail head, is progressing off site ahead of Easter.

Trail map, rider information and trail marker signage will be in place over the coming weeks.

Construction has started on the Oriental Claims Bridge (pictured below). This work is important for the finalisation of the first 10km of trails and links the Oriental Express and Mine Bender trails, creating a loop ride from Livingstone Park to the Oriental Claims and back.

Share Project Update 21/03/2023 on Facebook Share Project Update 21/03/2023 on Twitter Share Project Update 21/03/2023 on Linkedin Email Project Update 21/03/2023 link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>