May 2026

Progress is continuing at Livingstone Park following the commencement of works in April.

Construction commencement

  • Construction contractor Jarvis Norwood mobilised to site on 20 April 2026 and has established the work area.
  • The existing (old) spillway has now been safely demolished.
  • Excavation works for the new spillway wall and rock apron are well underway.
  • Installation of the rock apron has commenced, forming a key component of the new structure.
  • Preparations are in progress for the upcoming concrete pour for the new spillway wall.
  • Prefabricated components for the new pedestrian bridge have been delivered to site, ready for installation at a later stage of the project.

Council appreciates the community’s patience while these important upgrades are undertaken to improve safety, resilience and accessibility within Livingstone Park.

Further updates will be provided as the project progresses.