Share Newmerella - Roadside Rest Area Improvements on FacebookShare Newmerella - Roadside Rest Area Improvements on TwitterShare Newmerella - Roadside Rest Area Improvements on LinkedinEmail Newmerella - Roadside Rest Area Improvements link
This project is now complete.
The Newmerella Roadside Rest Area improvements have revitalised the visitor rest-stop and gateway to the Rail Trail. The redevelopment of the rest area adjacent to the Princes Highway at Newmerella has provided more defined and safer access for heavy vehicle operators and the travelling public through improvement of traffic management, surfacing and drainage works.
The scope of the works include:
Kerb and channel installation works for safe movement of heavy vehicles and general traffic
Road pavement repair
Asphalt resurfacing
Formalisation of five heavy vehicle parking pays
line marking and signage.
Installation of drainage pits and pipes
Renewal of road signage
Picnic tables and chairs are on order, with expected delivery scheduled around October 2023.
Copies of the information sheet and concept plans are still available at the Orbost Service Centre - 1 Ruskin Street, Orbost.
This project is funded by the Department of Infrastructure, Transport, Cities and Regional Development through the Small Road Projects program.
The Newmerella Roadside Rest Area improvements have revitalised the visitor rest-stop and gateway to the Rail Trail. The redevelopment of the rest area adjacent to the Princes Highway at Newmerella has provided more defined and safer access for heavy vehicle operators and the travelling public through improvement of traffic management, surfacing and drainage works.
The scope of the works include:
Kerb and channel installation works for safe movement of heavy vehicles and general traffic
Road pavement repair
Asphalt resurfacing
Formalisation of five heavy vehicle parking pays
line marking and signage.
Installation of drainage pits and pipes
Renewal of road signage
Picnic tables and chairs are on order, with expected delivery scheduled around October 2023.
Copies of the information sheet and concept plans are still available at the Orbost Service Centre - 1 Ruskin Street, Orbost.
This project is funded by the Department of Infrastructure, Transport, Cities and Regional Development through the Small Road Projects program.
Share Construction works complete on FacebookShare Construction works complete on TwitterShare Construction works complete on LinkedinEmail Construction works complete link
Works are complete. Finishing off the area will be picnic tables and chairs - these are on order and we expect to install them in approximately October.
This project was funded by the Department of Infrastructure, Transport, Cities and Regional Development through the Small Road Projects program.
Share Project Update - 26 June 2023 on FacebookShare Project Update - 26 June 2023 on TwitterShare Project Update - 26 June 2023 on LinkedinEmail Project Update - 26 June 2023 link
Construction of the Newmerella roadside rest area is progressing well. Boxing for the splitter island on the western entrance, internal footpaths, and the splitter island on the eastern entrance has been prepared ready for concrete pouring. The existing road pavement has been removed and will be replace with asphalt.
Share Project Update 1 June 2023 on FacebookShare Project Update 1 June 2023 on TwitterShare Project Update 1 June 2023 on LinkedinEmail Project Update 1 June 2023 link
Kerb and channel construction has commenced at the eastern end of the rest area and the road leading to the Pony Club ground.
Share Project Update - 1 May 2023 on FacebookShare Project Update - 1 May 2023 on TwitterShare Project Update - 1 May 2023 on LinkedinEmail Project Update - 1 May 2023 link
Council contractors will mobilise to site on 8 May 2023 to commence works.