Project Update - 21 August 2023
The consultant is progressing well with the detailed design.
The detailed design is closely following the concept plans:
- several footpaths will be reviewed for upgrading to 1800mm widths to align with the Disability Act .
- where possible, shared paths will be investigated.
- the grassed areas between the service roads and Myer Street will have kerb and posts installed to prevent cars from parking on there.
- no change to access for either Silver Sands Caravan Park (33 Myer Street) or Sunnyside Caravan Park (60 Myer Street)
- Lambert Street will remain a two-way street.
- investigations are being undertaken to find out whether additional along Lambert Street can be included
- whilst angled parking is recommended, other parking options will be further explored.