Project Update 5/12/2022
The Mallacoota Skatepark redevelopment is delayed until after the Christmas Holidays, in order to avoid unnecessary disruptions over the busy peak period. The Contractor, Grind Projects Pty Ltd, has experienced lengthy delays with other projects due to the extreme weather.
The proposed works are due to commence early February 2023 and the contractor has advised the works should take approximately 8-10 weeks to complete. Council expect the site to be open for public use by the end of April 2023.
The Lions Foundation and Bendigo Bank (Grant Sponsor) have endorsed and approved this extension of time request.