21 August 2024
Remediation works are set to commence.
Paul Volk Contracting is scheduled to start the Bastion Point groyne remediation works onsite on 23 September 2024.
Rock blasting and testing has commenced at a local East Gippsland quarry to acquire the larger rocks which will support the groyne structure.
The northern boat ramp will remain open for use by mariners during the onsite works.
Due to the limited area available to perform these operations, there may be some temporary interruptions / delays for local mariners using the northern boat ramp when trucks are on-site delivering rocks for the essential repairs.
Traffic management will provide guidance to ensure safety and minimise delays.
The works are anticipated to be completed this November, ensuring the boat ramp is open and safer for use in time for the busy festive season; however, strong winds and large swell may impact the completion date.