Project Update 18/01/2023
The Builders have returned from their Christmas break.
- Plastering is 95 % completed.
- Some wall tiles have been installed.
- Some cabinetry installed.
- External brickwork is 95% complete.
- Toilet and shower partitioning site measured and ordered.
Works are currently on schedule