Project Update 17/01/2023

Screw pile installation and survey setout are complete. Council's building crew will complete the concreting works required before structural steel installation can begin.

Structural steel delivery has been pushed out until February/March 2023 due to supply issues. Once the structural steel is installed Council's building crew will install decking and structural timber.


Share Project Update 17/01/2023 on Facebook Share Project Update 17/01/2023 on Twitter Share Project Update 17/01/2023 on Linkedin Email Project Update 17/01/2023 link

This project is now complete.

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>