Project Update 17/01/2023
Screw pile installation and survey setout are complete. Council's building crew will complete the concreting works required before structural steel installation can begin.
Structural steel delivery has been pushed out until February/March 2023 due to supply issues. Once the structural steel is installed Council's building crew will install decking and structural timber.