Project Update 25/10/2022
Stage 2 of the bridge replacement is progressing and on schedule to be open to all traffic by Christmas.
- Installation of remaining beams will be completed by the end of the week.
- Concrete deck to be poured in November
- Handrail and guardrail installation to be completed by mid-December.