Project Update 23/11/2022
Bullock Island Bridge is on track to be open to traffic by Christmas 2022.
- Final Sub structure concrete pour was completed last week.
- Concrete approach slabs to poured by the end of next week.
- Footpath and railing to be installed in first week of December.
- Rock beaching and sheet pile installation to be completed second week of December.
- Asphalt road surface to be installed third week of December.
- Clean-up works and demobilisation will take place after the 10 January 2023.
Share Project Update 23/11/2022 on Facebook
Share Project Update 23/11/2022 on Twitter
Share Project Update 23/11/2022 on Linkedin
Email Project Update 23/11/2022 link
Consultation has concluded