Project Update 23/11/2022

Bullock Island Bridge is on track to be open to traffic by Christmas 2022.

  • Final Sub structure concrete pour was completed last week.
  • Concrete approach slabs to poured by the end of next week.
  • Footpath and railing to be installed in first week of December.
  • Rock beaching and sheet pile installation to be completed second week of December.
  • Asphalt road surface to be installed third week of December.
  • Clean-up works and demobilisation will take place after the 10 January 2023.