Project Update 23/05/2022

The replacement of Bullock island Bridge is progressing well, taking into account staff shortages and delays associated with COVID.

The relocation of services is nearing completing along with the road widening component. The installation of kerb and footpath will occur this month with rocks placed on road formation batters to assist with erosion. The contractor is expected to commence stage 2 of the bridge replacement within the next month.