07 May 2021
Face to face consultation opportunity with Senior Project Development Officer
12 May 2021
Face to face consultation opportunity with Senior Project Development Officer
19 May 2021
Face to face consultation opportunity with Senior Project Development Officer
21 May 2021
Face to face consultation opportunity with Senior Project Development Officer
02 June 2021
Face to face consultation opportunity with Senior Project Development Officer
07 June 2021
Survey closes
August 2021
Complete Detailed Design
December 2021
Commence Construction
May 2023
Detailed design complete
June 2023
Tender advertised
September 2023
Construction to commence
September 2024
Construction completed