Project Update - 11 July 2023
Works on the Bullock Island Masterplan Implementation continue to progress -
- Southern carpark civil component is complete
- Sandblasting jetty car park underway
- Street furniture and solar lighting to be installed once delivered
- Top soiling and seeding of transition areas underway
- Boardwalk design nearing completion; we estimate works will commence early August