Project Update - 13 December 2023

The resurfacing of the Peppercorn Park oval cricket pitch commenced at 7am today.

Council's works crew starting the new cricket pitch.

The pitch has been moved to a new location and height to suit the new oval size and contours.

Civil and drainage works are currently out to tender.

The new concrete for the pitch is anticipated to be installed next week, with Civil and Irrigation works to follow in the early New Year.

6000 square metres of new turf will be laid in March 2024 followed by oval fencing, goal posts and line marking.